The low-water crossing was contracted and constructed
in 1998. Table 2 provides a detailed breakdown of the construction
of this 70 ft bridge that crossed a waterway with an 8500 ac watershed.
Tasks for the concrete bridge included 12 hours of permit data
collection and write up; six hours of field visits to collect
bids; 16 hours of culvert and form transport; and 80 hours for
culvert installation. Finally 16 hours were spent pouring concrete.
| 130 hours @ $12.50/hour on bridge |
$ 1625 |
| 120 yd3 of concrete @ $75/yd3 |
$ 9000 |
| 8 36 in. x 20 ft culverts @ $300/ea. |
$ 2400 |
| 4 24 in. x 20 ft culverts @ $240/ea. |
$ 960 |
| 30 tons of gravel delivered @ $6.25/ton |
$ 187 |
| 40 hours of backhoe @ $45/hour |
$ 1800 |
| 2 rolls of reinforcement wire at $65.00/roll |
$ 130 |
| Estimated profit for contractor |
$ 6897 |
| Total |
$23,000 |
|
TABLE 2. Construction time
and costs for
the 70 ft low-water concrete and pipe crossing. |